Water Reclamation Projects
Objective
The purpose of this project is to implement the recommended capital improvements to the collection system and to the Water Reclamation Facility as outlined in the WRF Master Plan.
Project Milestones
Final Master Plan | February 2018 |
City Council Master Plan presentation | March 2018 |
City Council Water Reclamation Projects presentation | October 2018 |
City Council 2020-2023 Utility Rate presentation | November 2018 |
2020-2023 Wastewater Rate increases approved | December 2018 |
City Council CMAR presentation |
January 2019 |
City Council approval to use CMAR project delivery method | January 2019 |
Carollo design contract approved |
August 2019 |
McCarthy CMAR contract approved |
March 2020 |
Current Documents, presentations, and handouts
Wastewater Treatment and Collection System Master Plan
Wastewater Treatment and Collection System Master Plan Appendices
City Council Presentation 10152018
City Council Presentation 03102020
2020-2023 Utility Rate Presentation 11132018
Archived Documents, Presentations, and Handouts
City Council Presentation 03272018