Project Timeline:

February 2008

Administration offices, Daycare Delivery, and Technical Services moves to 132 N. Dakota Ave (City Hall Annex - First Floor)

 Complete

March 2008

Library Staff move out of North section of Library.
Close book drop on East side of building.
Shift books in general collection to make room for construction in North section of building.

 Complete

April 9-10, 2008 Close Main Library for 2 days to rearrange book stacks. Close East entrance.

Complete

April 17, 2008   Groundbreaking ceremony, 10:30 a.m.

Complete

April 17, 2008 Construction begins on Phase 1 (North section).
April 2008 Remove asphalt from parking lot North of Library

Complete

April 24, 2008     Building demolition begins
May 2008 Work on utilities
May 2008 Excavation for North section expansion
June 2008 Pour foundation

April 2009

Move library collection and staff into new North section of building. Begin construction on South section.

 

April 2010

Construction complete.